Thursday, April 18, 2024

      Subscribe Now!

 

spot_img
spot_img
Greek CommunityCultureSteel Company sends workers to install steel plates at the Leounes/ Pan...

Steel Company sends workers to install steel plates at the Leounes/ Pan Laconian Museum

Hellenic News
Hellenic News
The copyrights for these articles are owned by HNA. They may not be redistributed without the permission of the owner. The opinions expressed by our authors do not necessarily reflect the opinions of HNA and its representatives.

Latest articles

Dear Hellenic News:
For a few days now work to raise the western and southwest walls by approximately 2 feet and come at the same level with the other sides of the building erected this summer.
Tomorrow and Thursday, we expect to strip the walls from the concrete forms. Doing this we finish all of the concrete work with walls.
 
At the top of the walls most of the concrete pockets need to be closed with cement blocks from outside before the installation of steel beams next week.
Also this week it is expected to raise  walls of 28 inches high between the five columns close to the theater. On the top, we will sit fixed glass with a metal frame between columns.
 
We have a small list with preparations needed to be completed before the arrival of steel beams and steel company workers early next week. We could do this after the steel beams are in place but it is easier now with the good weather we have.
 
Best wishes,
Ilias
 
 Ilias Tomazos, Director
PAIDEIA Study Abroad Programs in Greece
Center for Hellenic Studies PAIDEIA
28 Dog Lane, P.O.BOX 818, Storrs, CT 06268

 

The copyrights for these articles are owned by the Hellenic News of America. They may not be redistributed without the permission of the owner. The opinions expressed by our authors do not necessarily reflect the opinions of the Hellenic News of America and its representatives.

Get Access Now!

spot_img
spot_img
spot_img